Case 31: DHCP v6 tests with tagged hosts: 4 clients attached to switch directly and 1 server attached to switch directly, with 3 ONOS instances - FAIL

  • 31.1 Apply cell to environment - PASS (tick)
  • 31.2 Uninstalling Atomix - PASS (tick)
  • 31.3 Uninstalling ONOS package - PASS (tick)
  • 31.4 Installing Atomix - PASS (tick)
  • 31.5 Installing ONOS package - PASS (tick)
  • 31.6 Set up ONOS secure SSH - PASS (tick)
  • 31.7 Checking ONOS service - PASS (tick)
  • 31.8 Starting ONOS CLI sessions - PASS (tick)
  • 31.9 Checking ONOS nodes - PASS (tick)
  • 31.10 Checking ONOS applications - PASS (tick)
  • 31.11 Starting Mininet Topology - PASS (tick)
  • 31.12 Verify host IP address assignment in ONOS - FAIL (error)
    • Verify ONOS host IP failed
  • 31.13 Stopping Mininet - PASS (tick)
    • Skipping the rest of this case.

Case 41: DHCP v4 tests with dual-homed hosts: 4 clients attached to switch directly and 1 server attached to switch directly, with 3 ONOS instances - PASS

...

hosts

...

: 4 clients attached to switch directly and 1 server attached to switch directly, with 3 ONOS instances - FAIL

...

  • 51.1 Apply cell to environment - PASS (tick)
  • 51.2 Uninstalling Atomix - PASS (tick)
  • 51.3 Uninstalling ONOS package - PASS (tick)
  • 51.4 Installing Atomix - PASS (tick)
  • 51.5 Installing ONOS package - PASS (tick)
  • 51.6 Set up ONOS secure SSH - PASS (tick)
  • 51.7 Checking ONOS service - PASS (tick)
  • 51.8 Starting ONOS CLI sessions - PASS (tick)
  • 51.9 Checking ONOS nodes - PASS (tick)
  • 51.10 Checking ONOS applications - PASS (tick)
  • 51.11 Starting Mininet Topology - PASS (tick)
  • 51.12 Verify host IP address assignment in ONOS - FAIL (error)
    • Verify ONOS host IP failed
  • 51.13 Stopping Mininet - PASS (tick)
    • Skipping the rest of this case.

Case 61: DHCP v4 tests with dual-homed tagged hosts: 4 clients attached to switch directly and 1 server attached to switch directly, with 3 ONOS instances - PASS

  • 61.1 Apply cell to environment - PASS (tick)
  • 61.2 Uninstalling Atomix - PASS (tick)
  • 61.3 Uninstalling ONOS package - PASS (tick)
  • 61.4 Installing Atomix - PASS (tick)
  • 61.5 Installing ONOS package - PASS (tick)
  • 61.6 Set up ONOS secure SSH - PASS (tick)
  • 61.7 Checking ONOS service - PASS (tick)
  • 61.8 Starting ONOS CLI sessions - PASS (tick)
  • 61.9 Checking ONOS nodes - PASS (tick)
  • 61.10 Checking ONOS applications - PASS (tick)
  • 61.11 Starting Mininet Topology - PASS (tick)
  • 61.12 Verify host IP address assignment in ONOS - PASS (tick)
  • 61.13 Verify IP address assignment from hosts - PASS (tick)
  • 61.14 Stopping Mininet - PASS (tick)
  • 61.15 Copying karaf logs - PASS (tick)

Case 71: DHCP v6 tests with dual-homed tagged hosts: 4 clients attached to switch directly and 1 server attached to switch directly, with 3 ONOS instances - FAIL

...

  • Verify ONOS host IP failed

...