- 16.1 Balancing mastership of switches - PASS
Case 1000: Host Intents Test - 3 NODE(S) - OF 1.0 -
...
FAIL
This test case tests Host intents using 3 node(s) cluster; Different type of hosts will be tested in each step such as IPV4, Dual stack, VLAN etc; The test will use OF 1.0 OVS running in Mininet
- 1000.1 IPV4: Add and test host intents between h1 and h9 - PASS
- 1000.2 DUALSTACK1: Add host intents between h3 and h11 - PASS
- 1000.3 DUALSTACK2: Add host intents between h1 and h11 - PASS
FAIL
- Assertion Result for dualstack2 host intent
- Initial Intent State Passed
- Initial Flow State Passed
- Initial Ping Passed
- Link Down Passed
- Link Down Intent State Passed
- Link Down Flow State Passed
- Link Down Topology State Failed
- Link Down Pingall Passed
- Link Up Passed
- Link Up Intent State Passed
- Link Up Flow State Passed
- Link Up Topology State Passed
- Link Up Pingall Passed
- Remove Intents Passed
- 1000.4 1HOP: Add host intents between h1 and h3 - PASS
- 1000.5 VLAN1: Add vlan host intents between h4 and h12 - PASS
- 1000.6 VLAN2: Add inter vlan host intents between h13 and h20 - PASS
- 1000.7 Confirm that ONOS leadership is unchanged - PASS
...